TRAFFIC IMPACTS, WEEK OF SEPTEMBER 13, 2021

MAINLINE I-515 (US 95) SOUTHBOUND, Boulder Hwy to Flamingo Rd

WHAT:
Nightly lane restrictions
WHEN: Nightly, Monday 9/13 - Thursday, 9/16: Each night at 8pm, I-515 SB will be reduced to two lanes. By 9pm, I-515 SB will be reduced to one lane. All lanes will reopen by 5am the following morning.


BOULDER HWY ON-RAMP to I-515 (US 95) SOUTHBOUND
WHAT: Nightly ramp closure
WHEN: Nightly, Monday 9/13 - Thursday, 9/16: Each night, this ramp will be closed from 9pm until 5am the next morning.


DESERT INN RD under I-515 (US 95)
WHAT:
ROAD CLOSED to motorists and pedestrians WHEN: Monday, 9/13 at 9pm until Friday, 9/17 at 5am.

DESERT INN ROAD CLOSURE DETOUR

Casino Center on-ramp to I-515 (US 95) NB to close for 6 weeks starting 9/23

As a part of the next phase of construction on NDOT's I-515 Viaduct Rehab project, the Casino Center Blvd on-ramp to I-515 Northbound will close the night of Thursday, September 23. This ramp will be closed until mid-November.

Traffic Impacts: Week of September 19

Closures subject to change.

Sunday night, 9/19

I-515 NB reduced to one lane, Eastern Ave to Las Vegas Blvd, 11pm-6am

Monday night, 9/20

I-515 NB reduced to one lane, Las Vegas Blvd to I-15, 11pm-6am

Tuesday night/Wednesday morning, 9/21-9/22

I-515 SB reduced to one lane, I-15 to Las Vegas Blvd, midnight - 5am

Wednesday night/Thursday morning, 9/22-9/23

1. Eastern Ave on-ramp to I-515 NB closed, 9pm - midnight
2. I-515 NB off-ramp to Las Vegas Blvd closed, midnight - 2am 
3. Las Vegas Blvd on-ramp to I-515 NB closed, 2am-4am
4. Casino Center Blvd on-ramp to I-515 NB closed, 4am-6am

Thursday night/Friday morning, 9/23-9/24

1. Casino Center Blvd on-ramp to I-515 NB closed at 11pm for six weeks
2. Eastern Ave on-ramp to I-515 NB closed, 9pm-12am
3. I-515 NB reduced to one lane, Eastern Ave to I-15, 11pm-6am
4. I-515 NB off-ramp to Las Vegas Blvd closed, midnight - 3am
5. Las Vegas Blvd on-ramp to I-515 NB closed, 3am-6am

Starting Friday morning, Sept 24

I-515 will continue to have two travel lanes in each direction between Eastern Avenue and I-15; all traffic lanes will be shifted to the south side and center of the freeway as viaduct rehab work continues on the north side.

I-515 (US 95) is currently reduced to 2 lanes from I-15 to Eastern Ave through the end of 2022.

Click the image below to download a PDF.

Subscribe to text alerts

Text 515PROJECT to 775-242-9168

What to expect during the project

NDOT's I-515 Viaduct Rehab project, which started construction June 27, 2021, will last approximately one year. During this time, there will be lane reductions on I-515 (US 95) between the Spaghetti Bowl and Eastern Avenue, and multiple ramp closures. All current and upcoming closures will be posted on this page. To stay updated, please use the forms below to sign up for text updates and join our email list. Thank you for your interest in the I-515 Viaduct Rehab project!