LV Blvd Ramp
LV Blvd ramp
LV Blvd southbound off- ramp
Joints are complete on the LV Blvd off-ramp
Additional drainage
Barrier shift in preparation for LV Blvd ramp closure
Slip form barrier rail
Barrier shift preparation
Bump grinding
Bump grinding at LV Blvd off-ramp
Replacement of median barrier rail
Beginning the median barrier rail replacement
Median Barrier Rail Replacement
Median Barrier Rail Replacement
Median Barrier Rail Pour
Median Barrier Rail Pour
Marking location for permanent median barrier rail
Preparing to pour concrete for new median barrier rail
Median barrier rail replacement
Median barrier rail replacement
Machine pouring the replacement barrier rail
Pouring the barrier rail replacement
Preparing new signage
Pre-stage overhead signs below the I-515
Pre-stage overhead signs below the I-515
Slope grading and preparation for concrete valley gutter
Milling the paving transitions
Milling the paving transitions
Paving I-15 ramps to US 95 South
Paving I-15 ramps to US 95 South
Paving I-515 at US 95 South
Paving I-515 at US 95 South
Paving at I-515 and Casino Center Boulevard
Ramp transition grind
Eastern Avenue Bridge Demo & Reconstruction
Desert Inn Bridge Demo & Reconstruction
November 2021
South half of the new I-515/Eastern Ave bridge deck
Preparing for pavement near the new drainage improvements on the Eastern Ave offramp
Three out of six large, steel beams placed for reconstruction of the south half of the I-515/Eastern Ave bridge
Drainage improvements on the Eastern Ave offramp to help collect water runoff and protect the roadway
Second steel beam being placed for reconstruction of the Desert Inn bridge
Eastern Avenue deck rebar being placed
Placing polymer (poly) overlay on I-515 near the Casino Center offramp
Poly overlay helps protect roadway surfaces from tire wear and can easily be removed and replaced
Poly overlay continues on I-515 near the Casino Center ramp
Poly overlay continues on I-515 near the Casino Center ramp
Pan decking (metal floor decking) at the Desert Inn bridge
Wet cure blankets on Eastern Ave bridge deck
October 2021
Storm drain being installed on southbound I-515 at the Eastern offramp
Traffic shift on I-515 near Desert Inn, in preparation for bridge demo starting Oct. 25
I-515 bridge near Desert Inn prepped for demo
Demolition of the east half of the I-515/Eastern Ave bridge
Repairs to the Las Vegas Blvd on-ramp to I-515 (US 95) NB
September 2021
Desert Inn
Crews work to reconstruct a portion of the I-515 bridge deck over Desert Inn Rd.
I-515 Overnight
NDOT shifted barrier rail, changed striping, and closed the Casino Center on-ramp to I-515 NB overnight on 9/23.
I-515 NB Shift
The I-515 NB lanes have been shifted to the center of the deck north of Las Vegas Blvd so crews can continue viaduct repair work.